Home > Trane > Cooler > Trane Rtaaiom3 Manual

Trane Rtaaiom3 Manual

    Download as PDF Print this page Share this page

    Have a look at the manual Trane Rtaaiom3 Manual online for free. It’s possible to download the document as PDF or print. UserManuals.tech offer 12 Trane manuals and user’s guides for free. Share the user manual or guide on Facebook, Twitter or Google+.

    							51RTAA-IOM-3
    Table 4
    Liquid Line Size for Horizontal and/or Downflow Lines
    Circuit Size: Liquid Line Size (OD”)Total Equiv. Length (Ft) 100 Ton 85 Ton 70 Ton25 1 1/8 1 1/8 1 1/8
    50 1 3/8 1 1/8 1 1/8
    75 1 3/8 1 3/8 1 3/8
    100 1 3/8 1 3/8 1 3/8
    125 1 3/8 1 3/8 1 3/8
    150 1 5/8 1 3/8 1 3/8
    175 1 5/8 1 5/8 1 5/8
    200 1 5/8 1 5/8 1 5/8
    225 1 5/8 1 5/8 1 5/8
    250 1 5/8 1 5/8 1 5/8
    275 1 5/8 1 5/8 1 5/8
    300: 1 5/8 1 5/8 1 5/8
    Table 5
    Equivalent Lengths of Non-Ferrous valves and Fittings
    Line Size Globe Angle Short Long
    Inches OD Valve Valve Radius ELL Radius ELL
    1 1/8 87 29 2.7 1.9
    1 3/8 102 33 3.2 2.2
    1 5 /8 115 34 3.8 2.6
    2 1/8 141 39 5.2 3.4
    2 5/8 159 44 6.5 4.2
    3 1/8 185 53 8.0 5.1
    3 5/8 216 66 10.0 6.3
    4 1/8 248 76 12.0 7.3
    Reproduced by permission of Air conditioning and Refrigeration Institute.
    Line Sizing
    Equivalent Line Length
    To determine the appropriate size for
    field installed liquid and suction lines, it
    is first necessary to establish the
    equivalent length of pipe for each line.
    An initial approximation can be made
    by assuming that the equivalent length
    of pipe is 1.5 times the actual length of
    pipe. These assumed lengths can then
    be used with the appropriate tables in
    the Liquid Line Sizing section and the
    Suction Line Sizing sections which
    follow.
    It is also necessary to know the
    capacity (tons) of each circuit. Circuit
    capacities for each RTAA unit are listed
    in Table 3.The following are examples of how to
    determine line sizes.
    Liquid Line Sizing
    This example uses the unit installation
    shown in Figure 31 and assumes an 85
    ton circuit. The actual length of field
    installed piping is 117 feet (80 + 8 + 8 +
    21). Using the factor of 1.5, the
    equivalent line length is 175 feet.From Table 4, for horizontal and/or
    downflow liquid lines, and assuming
    an 85 ton circuit, 175 feet of equivalent
    line requires a liquid line with an OD of
    1 5/8 in.
    There are 6 long-radius elbows in this
    example. Using Table 5 and the pipe
    OD of 1 5/8 in., these fittings represent
    15.6 feet (6 elbows @ 2.6 feet each).
    Therefore our new equivalent line
    length is 132.6 feet (117 +15.6).
    Referring back to Table 4, an 85 ton
    circuit with 132.6 feet of equivalent pipe
    length (use the dimension closest to
    the calculated dimension) can use a
    pipe O.D. of 1% in. rather than 1 5/8 in.
    From Table 5 we see that the 6 elbows
    of 1 3/8 in. have an equivalent pipe
    length of 13.2 feet (6 elbows @ 2.2 feet
    each). This further reduces the
    equivalent pipe length to 130.2 feet
    (117 + 13.2), and, as shown in Table 4,
    still allows the use of 1 3/8 in. O.D. pipe.
    Table 3
    RTAA Circuit Capacities
    Model Circuit 1 Circuit 2130 70 70
    140 70 70
    155 85 70
    170 100 70
    185 100 85
    200 100 100 
    						
    							52
    RTAA-IOM-3
    Figure 31 
    Remote Evaporator Piping Example 
    						
    							53RTAA-IOM-3
    Suction Line Sizing
    This example uses the unit installation
    shown in Figure 31 and assumes a 100
    ton circuit. As in the liquid line sizing
    example, the equivalent pipe length
    must first be determined. It must also
    be determined what portion of the pipe
    is “horizontal and/or downflowing”
    and what portion is “horizontal and/or
    upflowing.”
    In Figure 31, the actual length of field
    installed piping is 100 feet (20 + 5 + 75).
    Using the factor of 1.5, the equivalent
    line length is 150 feet. The suction line
    has an elevation of 20 feet and consists
    of horizontal and vertical (upflowing)
    sections, which must be sized
    separately.
    The two vertical sections are separated
    by a small horizontal section. The total
    distance is 25 feet (20 +5). The first
    approximation of equivalent pipe
    length is 37.5 feet (1.5 times 25).
    Referring to Table 6 for a horizontal
    and/or upflow suction line on a 100 ton
    circuit with 37.5 feet of line, the pipe
    O.D. should be 3 1/8 in.Add the 75 feet of horizontal and/or
    downflow line to the 45.4 feet of
    horizontal and/or upflow line, resulting
    in 120.5 of equivalent pipe length. Table
    7 at 125 feet (use the dimension closest
    to the calculated dimension) indicates
    the use of 4 1/8 in. O.D. pipe. Therefore,
    the 4 1/8 in line will have to be reduced
    for the vertical sections of the line and
    expanded again for the horizontal
    sections. There are four long-radius elbows in
    this section of piping. Using Table 5
    and the pipe OD of 3 1/8 in., these
    fittings represent 20.4 feet (4 elbows @
    5.1 feet each). Therefore our new
    equivalent line length is 45.4 feet (25 +
    20.4). Table 6 indicates that 45.4
    equivalent feet still permits the use of 3
    1/8 in. O.D. pipe.
    In sizing the horizontal and/or
    downflow portion of the suction line, it
    is necessary to account for the total
    equivalent length of the line.
    Note: In this example, the horizontal
    line is pitched downward in the
    direction of flow
    Using Table 7 and 150 feet of
    equivalent pipe length for a 100 ton
    circuit, a pipe O.D. of 4 1/8 in. is
    specified. There are no fittings in the 75
    foot horizontal run, so no equivalent
    fitting lengths need to be determined.
    Table 6
    Suction Line Size for Horizontal and/or Upflow Lines
    Circuit Size: Suction Line Size (OD”)Total Vertical Equiv. Length (Ft) 100 Ton 85 Ton 70 Ton50: 3 1/8 3 1/8 2 1/8
    75: 3 1/8 3 1/8 2 1/8
    100: 3 1/8 3 1/8 2 1/8
    Table 7
    Suction Line Size for Horizontal and/or Downflow Lines
    Circuit Size:
    Total Equiv. Length (Ft) Suction Line Size (OD”)
    (Including vertical section, if any) 100 Ton 85 Ton 70 Ton50: 3 1/8 3 1/8 2 5/8
    75: 3 1/8 3 1/8 2 5/8
    100: 3 1/8 3 1/8 3 1/8
    125: 4 1/8 3 1/8 3 1/8
    150: 4 1/8 3 1/8 3 1/8
    175: 4 1/8 4 1/8 3 1/8
    200: 4 1/8 4 1/8 3 1/8
    225: 4 1/8 4 1/8 3 1/8
    250: 4 1/8 4 1/8 3 1/8
    275: 4 1/8 4 1/8 3 1/8
    300: 4 1/8 4 1/8 3 1/8 
    						
    							54RTAA-IOM-3
    Piping Installation
    Procedures
    The outdoor unit and the evaporator
    are shipped with a 25 psig holding
    pressure of dry nitrogen. Do not relieve
    this pressure until field installation of
    the refrigerant piping is to be
    accomplished. This will require the
    removal of the temporary pipe caps.
    Note: Use Type L refrigerant-grade
    copper tubing only.
    The refrigerant lines must be isolated
    to prevent line vibration from being
    transferred to the building. Do not
    secure the lines rigidly to the building
    at any point.
    All horizontal suction lines should be
    pitched downward, in the direction of
    flow, at a slope of 1/2 in. per 10 feet of
    run, This allows for larger line size,
    which will improve unit efficiency.
    Do not use a saw to remove end caps,
    as this may allow copper chips to
    contaminate the system. Use a tubing
    cutter or heat to remove the end caps.
    When sweating copper joints, flow dry
    nitrogen through the system. This
    prevents scale formation and the
    possible formation of an explosive
    mixture of R-22 and air. This will also
    prevent the formation of toxic
    phosgene gas, which occurs when
    refrigerant is exposed to open flame.
    WARNING: To prevent Injury or
    death, due to explosion and/or
    inhalation of phosgene gas,
    purge the system thoroughly
    while sweating connections. Use
    a pressure regulator in the line
    between the unit and the high
    pressure nitrogen cylinder to
    avoid over-pressurization and
    possible explosion.
    Refrigerant Sensors
    The suction line refrigerant sensors
    must be installed by the contractor
    installing the refrigerant piping. The
    sensors are pre-wired and each is
    “wire-tied” to its respective liquid line.
    Fittings and adapters for mounting of
    the sensors are located in the remote
    evaporator terminal box. See Figure 32
    for mounting instructions. 
    						
    							55RTAA-IOM-3
    Figure 32
    Customer Interconnect Wiring for
    RTAA Outdoor unit with Remote Evaporator –
    130 to 200 Tons
    2306-9133A 
    						
    							56RTAA-IOM-3
    Leak Test and Evacuation
    After installation of the refrigerant
    piping, thoroughly test the system for
    leaks. Pressure test the system at
    pressures required by local codes.
    Immediately before evacuation, install
    the liquid line filter cores. These will be
    shipped with the evaporator.
    Note: Do not install these before the
    circuit is ready for evacuation, as the
    cores will absorb moisture from the
    atmosphere.
    For field evacuation, use a rotary-type
    vacuum pump capable of pulling a
    vacuum of 100 microns or less. Follow
    the pump manufacturer’s instructions
    for proper use of the pump. The line
    used to connect the pump to the
    system should be copper and be the
    largest diameter that can be practically
    used. A larger line size with minimum
    flow resistance can significantly reduce
    evacuation time.
    Use the ports on the compressor
    suction service valves and the liquid
    line shutoff valves for access to the
    system for evacuation. Insure that the
    compressor suction service valve, the
    liquid line shutoff valve, the oil line
    shutoff valve and any field installed
    valves are open in the proper position
    before evacuating.
    Insulate the entire suction line and the
    suction accumulator line. Where the
    line is exposed to the weather, wrap it
    with weatherproof tape and seal with
    weatherproof compound.
    Refrigerant and
    Additional Oil Charge
    Refrigerant Charge
    Determination
    The approximate amount of refrigerant
    charge required by the system must be
    determined by referring to Table 8 and
    must be verified by running the system
    and checking the liquid line
    sightglasses.
    Table 8
    System Refrigerant Charge
    Circuit Size Lbs. of R-2270 130
    85 165
    100 170
    To determine the appropriate charge,
    first refer to Table 8 to establish the
    required charge required without the
    field-installed piping. Next, determine
    the charge required for the field-
    installed piping by referring to Table 9.
    Table 9
    Field-installed Piping Charge
    Pipe O.D. Suction Liquid
    (inches) Line Line
    1 3/8 1.2 63.0
    1 5/8 1.7 89.2
    2 1/8 2.9 155.2
    2 5/8 4.5 239.4
    3 1/8 6.4 —
    4 1/8 11.3 —
    Note: The amounts of refrigerant listed
    in Table 9 are based on 100 feet of pipe.
    Actual requirements will be in direct
    proportion to the actual length of
    piping.
    Note: Table 9 assumes:
    Liquid Temperature = 100 F
    Suction Temperature = 35 F
    Suction Superheat Temperature = 8 FThe approximate amount of refrigerant
    is therefore the sum of the values
    determined from Tables 8 and 9.
    Example:
    Determine the approximate amount of
    charge required for an RTAA 200 ton
    unit with a remote evaporator that is
    located 75 feet away (i.e. the actual
    length of field installed pipe is 75 feet
    for each suction line and liquid line).
    Assume that the suction lines have
    been previously determined to be 4 1/8
    in., O.D. and the liquid lines are 1 3/8 in.
    O.D.
    A 200 ton unit has two 100 ton circuits.
    From Table 8 above, a 100 ton circuit
    requires 170 lbs. of R-22. In addition,
    the 4 1/8 in. 0. D. suction line for the 100
    ton circuit will require 11.3 lbs. per 100
    feet of the 75 feet of line will therefore
    require 8.5 lbs. (11.3 times 75/100).
    Similarly from Table 9, the 1 3/8 in. O.D.
    liquid line will require 47.3 lbs. of R-22
    (63 times 75/100). The total R-22 charge
    for the 100 ton circuit will be 225.8 lbs.
    (170 + 8.5 + 47.3). And because the
    RTAA 200 has two 100 ton circuits, the
    total system charge will be twice as
    much, or 461.6 lbs.
    Oil Charge Determination
    The unit is factory charged with the
    amount of oil required by the system,
    without the field-installed piping. The
    amount of additional oil required is
    dependent upon the amount of
    refrigerant that is added to the system
    for the field-installed piping.
    Use the following formula to calculate
    the amount of oil to be added:
    Pints of Oil (Trane Oil-15) = lbs. of
    refrigerant added for field-installed
    piping/18.375
    From the example above, in which the
    weight of the additional refrigerant
    added for the field-installed piping was
    55.8 lbs. (47.3 + 8.5), the amount of oil
    to be added equals 3 pints (55.8/18.375)
    per circuit. 
    						
    							57RTAA-IOM-3
    Installation –
    Electrical
    Figure 33
    Warning Label
    General
    Recommendations
    WARNING: The Warning Label
    shown in Figure 33 is displayed
    on the equipment and shown on
    wiring diagrams and schematics.
    Strict adherence to these
    warnings must be observed.
    All wiring must comply with local
    codes and the National Electric Code.
    Typical field wiring diagrams are
    shown in Figures 34 thru 36. Minimum
    circuit ampacities and other unit
    electrical data are on the unit
    nameplate and are shown in Table 10.
    See the unit order specifications for
    actual electrical data. Specific electrical
    schematics and connection diagrams
    are shipped with the unit.
    Caution: To avoid corrosion and
    overheating at terminal
    connections, use copper
    conductors only.
    Do not allow conduit to interfere with
    other components, structural members
    or equipment.
    Control voltage (115V) wiring in
    conduit must be separate from conduit
    carrying low voltage (
    						
    							58RTAA-IOM-3
    (Continued on Next Page)Figure 34
    Typical Field Wiring for
    RTAA Packaged Unit –
    130 to 200 Tons 
    						
    							59RTAA-IOM-3
    (Continued from Previous Page)
    See Notes on Next Page 
    						
    							60RTAA-IOM-3
    Figure 34 (Continued from Last Page)
    Typical Field Wiring for
    RTAA Packaged Unit –
    130 to 200 Tons
    2306-9123-A 
    						
    All Trane manuals Comments (0)

    Related Manuals for Trane Rtaaiom3 Manual